Saturday, September 27, 2008

Saturday update

Today I used a razor blade to score around the bases of the recessed lights where they contact the drywall and are painted over. Hopefully the electrician will be able to dislodge the lights to rewire them without disturbing the paint job too much. (Below is a shot of the paint damage around one of the lights, which I'll have to fix eventually. The paint ripped away from the soffit when the light was dislodged.)

Thursday, September 25, 2008

Repaired, repainted ceiling where fan goes

Damage had been pretty bad when I extricated the ring of caulk from the ceiling. Now you would never know. Ready for the fan to be installed.

Electrical inspection

[Updated below.] Wednesday afternoon I got a call from the Home Depot District Services Manager saying the electrical inspector would be coming to my home today between 8 a.m. and 5 p.m. I also got a call from the electrical contractor saying the electrician would be here between 8 and 10. I called the City of North Miami and tried to get a more specific time of arrival, but they couldn't give me one. So I took today off from work as a vacation day.

The electrician got here at 9:00 (not the same one who was here last Friday) and we waited till almost 2:00 for the inspector. The inspector approved the latest work but then started probing around the recessed lights in the soffit, which were installed over a year ago when I had the ceiling redone. He said recessed lights can no longer be wired with "romex" (a heavy-duty plastic-coated wire, pictured)--and sure enough, these had been.

So, the next step is to schedule a time for the electrician to come back in and rewire the recessed lights, which will entail further damaging the ceiling where the lights are located (i.e., the soffit). As you know, I had spent so much time and energy awhile back correcting the handyman's sloppy details, spackling and sanding and then priming and painting the area with the correct paint.

The inspector will come back when the recessed lights are rewired and the drywall on the walls around the electrical boxes is repaired/replaced. Also, the recessed lights have to be left dangling so the inspector can see that they've been rewired properly--with flexible metal conduit. Meanwhile, I may loosen the recessed light housings from the soffit myself in an effort (maybe futile) to minimize the damage. We'll see. They're stuck to the drywall with paint.

P.S. Last night I (almost) painted the rest of the kitchen ceiling. (I ran out of paint.) It's ready for the fan to be installed, however.

Friday update: I've decided to score the drywall around the rims of the light housings with a razor blade or X-acto knife, cutting through the layers of paint and primer. Thus the electrician should be able to pull the housing out without taking my new paint job with it.

I didn't hear anything from anybody today about coming back in and doing more electrical work, etc.

Monday, September 22, 2008

Update

Last night while I was out at the store, I received a voice message from the lady at Home Depot in Atlanta. I returned the call and left a message.

I talked to her today. She said she would let me know what's going on with the electrical inspection, etc when she hears more from the District Services Manager.

Tonight I sanded around the electrical box for the ceiling fan and then primed the area. It looks pretty smooth now and will look even better when it's painted over. I don't think anyone would notice the repair job. Moreover, it will be obscured by the fan itself.

Next I'll begin repainting the square recessed area, starting with the edging. Then I'll use the roller. I want to have the ceiling totally finished before they install the new fan. I don't want to even attempt to paint it with the big, brand-new fan hanging there.

Sunday, September 21, 2008

The Permit

I almost forgot to mention that the electrician brought this on Friday. It covers all the work, including electrical and plumbing.

Painted the fan

This is the fan that was in the kitchen. The electrician took it down on Friday. Today I sprayed it white before it gets installed in the second bedroom. (I used Rust-Oleum Painter's Touch. Good stuff. No runs or spatters.)

I also removed the ring of caulk that had been applied around the base of the fan and which had stuck to the drywall. In the process, I damaged the drywall--the paper tore away in places. So I bought some contact cement at Target to glue the paper back to the ceiling. Then I spackled that area and will sand it tomorrow with the electric sander (more dust). Then the whole, square recessed area where the fan goes has to be painted with kitchen ceiling paint. (The handyman who created the ceiling used regular ceiling paint, which absorbs grease.)

Friday, September 19, 2008

'Rough' electrical installation complete

The electrician arrived shortly before 10:00 (i.e., right on time) and left at 5:23. He worked all day long without lunch or even a glass of water (unless he had some water down in his truck). Very nice guy.

There was some confusion over where to install the outlet for the microwave, which is going above the stove. The general contractor had made rough, pencil drawings in two places on the drywall (a few inches apart) and (roughly) crossed one of them out. That's where the electrician put the box (X marks the spot, right?). He said he'd move it if necessary. I wish he'd asked me about it, but it doesn't seem to be a big deal to him. So I'm not going to fret about it. Maybe it'll be fine where it is.

This was just the "rough" installation. I didn't know anything about that. The wiring is done but the new receptacles (the guts) and switch for the disposer have yet to be inserted into the boxes. The wiring has to be inspected first. Then he comes back in and finishes everything. Then it's inspected again.

He also took down the ceiling fan (see below), which they're going to re-install in the 2nd bedroom, and will replace it with another one for the kitchen (see early post). I'll spray the bedroom fan white so it will recede into the white ceiling (right now it's brushed aluminum--nice but too much of a statement in that room). The new one for the kitchen is also brushed aluminum and will match the finish on the cabinet handles, sink and faucet.

Since the cabinet above the fridge will block one of the recessed lights, he removed the light fixture and wired the two adjacent lights to each other. I'll have to do some repainting around those two fixtures when I finish off the rest of the ceiling, which will be easy to do now that the ceiling fan has been removed.

He said I'll also need to get a new plug for the stove, since the 220 outlets have changed since I bought the stove (a year and a half ago(?)).

I didn't have to fork out any money today.

P.S. The stove is now inoperable, so there will be no more cooking chili for a while.